Weekly Dose

 

Area 1. East St North Verge Parking:

  •   A. NEB Construction Site:

    • Impact: 23 parking spaces reinstated.

    • Dates: 10 October 2026. COMPLETE

  • B. Change of access road:

    • Impact: Temporary access road diverted through the East Street North verge parking.

    • Dates: 13 October – 27 October 2026. IN PROGRESS

  • C. East Street North Verge Parking:

    • Impact: Carpark closed for upgrading

    • Dates: 28 October – 14 December 2026 IN PROGRESS

 

Area 2: Northeast Building Landscapes works:

  • Impact: Diverted pedestrian access via Oasis Cafe

  • Dates: 10 October – 3 November 2026. IN PROGRESS

 

Area 3: East St South Verge Parking:

  • Impact:  ~23 car spaces to be made available.

  • Dates: Completion expected 26 October 2026. COMPLETE

 

Area 4: Emergency Department Southern Carpark

  • A. Eastern Hill water supply works:

    • Impact: one lane traffic control will be in place during works. Overnight works to occur.

    • Dates and times:
      Tuesday 3 November, 6pm to Wednesday 4 November, 3am
      Wednesday 4 November, 6pm to Thursday 5 November, 3am

  • B. Carpark Expansion

    • Impact: Increased construction vehicle movements, traffic control, and temporary traffic management arrangements will be in place.12 parking spaces temporarily unavailable.

    • Dates: 26 October 2026 – 26 February 2027. IN PROGRESS

 

For more information, please look out for the Disruption Notice specific to each activity, or contact awh.communications@awh.org.au